What is a knockdown rebuild?
A knockdown rebuild is when you demolish the existing house on your own block and build a new home on the same land. It is common in Melbourne's established inner and middle suburbs, including the inner west, where the land is often what people want to keep and the house is what they want to change. Because you already own the land, there is usually one main contract, the building contract, rather than the separate land and build contracts of a house and land package.
The steps below follow the order most projects take in Victoria. Councils differ in their forms and fees, so treat your own council's website as the final word for your address.
Step 1: What does the planning scheme allow on your block?
Start with a Planning Property Report for your address from VicPlan, the state's planning map. It shows the zone and the overlays that apply to the land, with links to the planning scheme.
- Heritage overlay. The Building and Plumbing Commission notes that a heritage overlay generally means a planning permit is also needed to demolish. If the council has not granted one, it must refuse consent to the demolition.
- Victorian Heritage Register. A building on the register needs the report and consent of the Executive Director under the Heritage Act 2017, through Heritage Victoria.
- Other controls. Some councils protect significant trees, and easements can limit where a new home can sit. Check both before you finalise a design.
- The new home. Whether building the new house needs a planning permit depends on the zone, the overlays and the size of the lot. Ask the council's planning team for your address.
Step 2: Choose a builder and a design, and have the site assessed
Before a builder can give you a firm price they will usually want a soil test and a survey of the block, because the slab, the drainage and any retaining depend on them. The design has to suit the block, the overlays and the street. Read what the price includes, and which items are allowances that can change, in what turnkey actually includes.
Home warranty insurance changed on 1 July 2026. For building contracts signed from that date for more than $20,000, on homes of three storeys or less, the builder must buy Home Warranty Insurance under a scheme run by the Building and Plumbing Commission. The Victorian Government says it covers lost deposits, incomplete building work, and defective or non compliant building work, and that you can claim once a problem is identified rather than only as a last resort. Ask the builder for the certificate before you pay a deposit.
Step 3: How does finance work for a knockdown rebuild?
If you are borrowing for the build, a construction loan is usually released in stages as the builder completes each part of the house, and the repayment grows with each stage. We explain the stages in how a construction loan draws down. Citadel Developments is not a lender and does not hold an Australian Credit Licence, so speak to a licensed broker early about what a lender will need from you and from the builder.
Step 4: Which approvals do you need to demolish?
- Report and consent from the council. Under section 29A of the Building Act 1993, the council's report and consent is needed where the demolition, together with any demolition in the previous three years, would be more than half the volume of the building, or where it affects a street facade. Demolishing a whole house meets that test. The council has 15 business days to respond.
- A building permit for the demolition. It is issued by a registered building surveyor, municipal or private. Some councils accept the application while other approvals are being assessed, but the permit is issued only once they are in place.
- An asset protection permit. Most Melbourne councils require one before demolition or building works that may affect the footpath, nature strip, kerb or drains, usually with a bond that is refunded once the council has inspected the assets after the works.
- Protection work for neighbours. The building surveyor can require work to protect a neighbouring property. It cannot start until the neighbour has agreed to it.
Step 5: Asbestos and services, before the house comes down
WorkSafe Victoria warns that asbestos can be present in buildings built before 1990. In Victoria all friable asbestos must be removed by a licensed removalist, and so must non friable asbestos once the job is more than 10 square metres or takes more than one hour in total in any seven days. Ask your demolition contractor how asbestos will be identified and who will remove it, and check that the removalist holds the right licence.
Gas, electricity, water and telecommunications need to be disconnected or made safe before demolition. Each provider arranges its own, so ask early and allow time for it in the timeline.
Step 6: The building permit and the build
The new home needs its own building permit. The building surveyor who issues it sets the mandatory inspections on the permit and follows the project through to the end. The build then moves through the usual stages: base or slab, frame, lock up, fixing and practical completion.
Step 7: Completion and handover
The building permit says whether the home needs an occupancy permit or a certificate of final inspection when it is finished. After that comes the practical completion inspection, handover and the defects period. We cover what to check in the defect period: what to inspect and when.
How long does a knockdown rebuild take?
There is no single timeline. It depends on whether a planning permit is needed, how long the council and the surveyor take, the size of the home and the builder's schedule. The one fixed clock in the demolition approvals is the council's 15 business days for report and consent. Ask the builder for a written timeline that shows each stage, from approvals to handover.
Most people move out for the whole project, whether into a rental, in with family or into another home they own. Plan where you will live before the demolition date is set.
What does a knockdown rebuild cost in Melbourne?
We do not publish dollar figures, because the real number depends on the block, the design and the builder. These are the cost categories to ask about, in writing, before you sign:
- Demolition, including removal of the old house and any outbuildings.
- Asbestos identification and licensed removal, if it is present.
- Disconnection of services, and reconnection for the new home.
- Council fees, permits and the asset protection bond.
- Site costs: soil test, survey, excavation, retaining, drainage and any fill.
- Design, drafting and engineering.
- The building contract itself, and which items are allowances rather than fixed prices.
- Protection work for neighbouring properties, if the surveyor requires it.
- Driveway, fencing, landscaping and window coverings, if they are not in the contract.
- Somewhere to live while the work is done.
What does a finished knockdown rebuild look like?
Two of the homes in our gallery are knockdown rebuilds, built by one of our building partners for their own clients: a curved brick home in Altona North and a black gable home in Maribyrnong. Each page lists the land size, the floor area and the finishes.
Where Citadel Developments fits
Citadel Developments is not a builder. We help people building a new home in Melbourne find a registered builder, keep the build and the finance timeline in step, and stay across the builder relationship from the contract to the defect inspection. If you are weighing up a knockdown rebuild, the short questionnaire takes about a minute, or read the eight steps, start to finish.