What do base price, fixed price and turnkey mean?
- Base price. The starting price a builder advertises for a design, usually on a flat block with standard inclusions. It commonly leaves out site costs, upgrades you saw in the display home, and things like the driveway, fencing and window coverings. There is no legal definition, so each builder decides what it covers.
- Fixed price. A building contract that states the price for the work described in the plans and specifications. Consumer Affairs Victoria says the law only allows certain changes to the price in a signed domestic building contract. A fixed price is only as complete as the plans, the specifications and the inclusions list it is attached to.
- Turnkey. A home that is finished and ready to live in or lease on the day you get the keys, with nothing left to buy or arrange. Turnkey is also not a legal term. We list every item to look for in what turnkey actually includes.
The three words answer different questions. Base price tells you where a design starts. Fixed price tells you how the contract handles the cost of the work. Turnkey tells you how much of the home is finished at handover. A quote can be one, two or all three.
Fixed price vs base price: what is the difference?
A base price is a starting point for a conversation. A fixed price is a number in a signed contract. The gap between them is made up of everything the base price left out and the builder adds once it knows the block and your selections. These are the categories to ask about, in writing, before you compare two builders:
- Site costs: the soil test, survey, excavation, any rock removal, retaining walls, drainage and fill. On a sloping block or reactive soil these can change the slab design.
- Connections: power, water, sewer, stormwater, gas where it is available, and the internet lead in.
- Requirements of the estate, the council or the planning scheme, such as facade rules, recycled water, a bushfire rating or an energy rating upgrade.
- Upgrades: anything in the display home that is not in the standard inclusions, from ceiling heights to benchtops.
- Items needed to move in or lease: driveway, fencing, landscaping, window coverings, flyscreens and appliances.
- Council and permit fees, and who pays them.
What are prime cost items and provisional sums?
Both are estimates inside a fixed price contract, so they are the parts of the price that can still change.
- Prime cost items are fixtures and fittings you have not yet selected, or whose exact price was not known when you signed, such as an oven, taps or tiles. Consumer Affairs Victoria says the contract can only estimate the price, which could be less than the final cost.
- Provisional sums are a reasonable estimate of the cost of work that cannot be priced exactly when you sign, such as excavation. Consumer Affairs Victoria warns that excavation costs could increase substantially if more work is needed.
Consumer Affairs Victoria advises avoiding prime cost items and provisional sums where possible, because they can make the final cost higher. Where they are used, the contract must include a detailed list of them with the estimated cost of each, and the builder must make a reasonable allowance for the nature and location of the site. You are entitled to a copy of the invoice, receipt or other document that shows the real cost. If the builder intends to charge more than the actual cost increase, the contract must say how the extra amount is worked out.
A quote with a low price and a long list of allowances is not cheaper than a quote with a higher price and very few. Add up the allowances, ask how each was estimated, and ask which ones the builder can fix before you sign.
Can a fixed price change after you sign?
Yes, but only in the ways the law allows. The main ones are variations, prime cost items and provisional sums.
- Variations are changes to the plans or specifications after the contract is signed. Consumer Affairs Victoria says both parties must agree to them in writing, with the new price and completion date, before the work is done.
- Prime cost items and provisional sums move to their real cost once it is known, as above.
- Cost plus contracts, where you pay the builder's costs plus a margin rather than a fixed price, cannot be used in Victoria for contracts under $1 million, and only in very limited circumstances above that. Consumer Affairs Victoria suggests getting legal advice if a builder asks you to sign one.
The rules are changing. The Domestic Building Contracts Amendment Act passed the Victorian Parliament on 11 September 2025, and Consumer Affairs Victoria says the new laws will take effect by 1 December 2026. They include a single process for variations to major domestic building contracts, and allow cost escalation clauses only in contracts of $1 million or more, adding no more than 5% to the price. Until they start, the current laws apply. Ask your conveyancer or solicitor which rules cover a contract you are about to sign.
What should you check before you sign the building contract?
- The builder is registered with the Building and Plumbing Commission.
- The plans and specifications describe the home you expect, with every fixture, fitting and finish named.
- Every prime cost item and provisional sum is listed with its estimate, and you know which ones you can remove by making your selections now.
- Site costs are fixed after a soil test and survey, not left as an estimate.
- The inclusions list covers everything needed to move in or lease, if you are paying for turnkey.
- The deposit is within the legal limit. In Victoria it is 5% for contracts of $20,000 or more.
- Progress payments are only for stages of work that are complete.
- You know when you will receive the Notice of Cover for Home Warranty insurance. The Building and Plumbing Commission says it applies to eligible contracts of more than $20,000 signed from 1 July 2026, and only when the builder is registered.
Consumer Affairs Victoria notes that you generally have five business days after signing to withdraw from a major domestic building contract, unless you got legal advice on it before you signed. Having a licensed conveyancer or solicitor review the contract before you sign is usually the better time to find a problem.
How this works in a house and land package
A house and land package usually has two contracts: one for the land and one for the build. The fixed price, the allowances and the inclusions all sit in the building contract. Site costs are often the hardest part to fix on a new estate lot, because the soil test can only be done once the lot exists. If the land is not yet titled, read titled land versus registration pending as well, because the building price may only be held for a set period.
Where Citadel Developments fits
Citadel Developments is not a builder and does not give legal advice. When we put a package forward, we check the building contract's inclusions list against a turnkey standard and ask the builder to fix site costs and remove allowances where it can, so the number you compare is close to the number you pay. A licensed conveyancer or solicitor reviews the contract itself. If you are comparing quotes now, the short questionnaire takes about a minute, or read the eight steps, start to finish.